Behind the Scene Photos From Today at CCPL!

𝐇𝐞𝐫𝐞 𝐚𝐫𝐞 𝐚 𝐟𝐞𝐰 𝐛𝐞𝐡𝐢𝐧𝐝 𝐭𝐡𝐞 𝐬𝐜𝐞𝐧𝐞 𝐩𝐡𝐨𝐭𝐨𝐬 𝐭𝐚𝐤𝐞𝐧 𝐭𝐨𝐝𝐚𝐲.☺️
️️☑ Most of our new carpeting was delivered today.
☑️ The public restroom fixtures have arrived and the tile on the floor and the walls is complete.
☑️ Cabinets in the meeting room and staff work areas have started being removed.
☑️ Library staff have been busy doing curbside services for our patrons. ☺️
There are still lots of books being checked out and returned each day.
☑️ Glue removal from the concrete in the main areas of the library is, for the most part, complete.
This is in preparation for the new carpeting that will be installed.
☑️ Electricians have been here this week, working on various items. They’ve finished the work on the new electrical floor boxes.
☑️ Staff have been super-busy boxing up as much stuff as we can, in preparation for phase two of our renovation project.
Phase two involves staff temporarily moving: our work spaces, equipment, supplies, etc. to the main (public) areas of our library.
This will allow work to begin on the behind-the-scenes areas (such as the storage room, staff workspaces, meeting room, etc.)
☑️ Before we reopen, we’ll need to thoroughly clean all of the bookshelves, countertops, etc.
If everything goes smoothly, we’re hoping to reopen during Lone Tree Days in July.
𝓣𝓱𝓪𝓷𝓴-𝔂𝓸𝓾 𝓯𝓸𝓻 𝔂𝓸𝓾𝓻 𝓹𝓪𝓽𝓲𝓮𝓷𝓬𝓮!
STAY TUNED for more updates about the progress of this exciting #InteriorRenovation